Below are flash cards simulation questions on the chapter Procurement management.
Both question and answer are given below.
Answer is hidden by giving the font color of text and background color as same.
To see the answer, pls highlight text by selecting it with mouse cursor.
1. What are different Types of contracts. (Too see answer, select text below with mouse/ cursor)
Answer:
4. What is Fixed price Award Fee (FPAF). (Too see answer, select text below with mouse/ cursor)
Answer: FPIF is potential award or penalty BUT FPAF is always award (not a compulsory fee)
Both question and answer are given below.
Answer is hidden by giving the font color of text and background color as same.
To see the answer, pls highlight text by selecting it with mouse cursor.
1. What are different Types of contracts. (Too see answer, select text below with mouse/ cursor)
Answer:
- Fixed price contract
- Time and Material contract
- Cost reimbursable
2. What do you know about Firm fixed price contract (who bears risk; How much is profit; what happens if scope changes). (Too see answer, select text below with mouse/ cursor)
Answer:
Firm fixed
Price contracts –FFP = setting a fixed total price for a defined product,
service, or result
·
Risk
is for seller (contractor). Profit is not known. Cost increases due to
adversities--> borne by seller
·
Most
common type. If scope changes, specs change, renegotiate
contract
3. What is Fixed price incentive Fee contract (FPIF). (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
·
Incentive
OR penalty – based on achieving agreed metrics
·
Final
contract price is determined after completion of work and evaluating
performance targets
·
Any
costs above ceiling price is responsibility of seller
Concept of “Point
of Total assumption” = target cost +[(ceiling price-target price)/buyer
ratio]
4. What is Fixed price Award Fee (FPAF). (Too see answer, select text below with mouse/ cursor)
Answer: FPIF is potential award or penalty BUT FPAF is always award (not a compulsory fee)
5. What is Fixed price
with Economic Price Adjustment Contracts. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
·
For
very long term contracts
·
Adjusted
for inflation, $ exchange, crude oil price hikes
6. What is Cost reimbursable contract. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Cost
reimbursable contracts = when scope is not precisely defined at the start or
when there are high risks, this type provides some flexibility to contractor
e.g. R&D projects
7. What is Cost Plus Fixed Fee. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Payments
to seller =All legitimate actual costs incurred + Fixed fee (determined at the
start);
Fee doesn’t change based on performance. It may
change if Scope changes;
8. What is Cost plus incentive Fee. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Payments
to seller = All legitimate actual costs incurred + [Fixed fee + Incentive based
on % of savings]
·
Fixed
Fee = Min fee or Target fee or Max fee
·
[Fixed fee + Incentive based on % of savings]
should not exceed max fee
·
If
no savings, cost exceeds the target, only min fee he will get. No incentives
· e.g. Target
cost 1,00,000, Fee (Min 9k, target 12k, max 14k), sharing ratio 80:20
· If
work finished for 95k seller gets 95k+
12k (i.e. target fee) + 20% of savings ( i.e. 100k – 95k = 5k) = 95k +12k+ 1k = 108k
· If
work finished for 85k seller gets 85k+
[12k + 20% of (1L – 85k)] = 85k + 15k-> but max fee is 14k, so 85k+14k = 99k
If work finishes for 1,20,000 , seller gets
120k+ 9k = 129k
9. what is Cost Plus Award Fee. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Payments
to seller = All legitimate actual costs incurred + Fee (determined based on
subjective performance, not fixed at start)
Award
= bonus
Cost plus incentive fee is potential award or
penalty BUT cost plus award fee is always potential award
10. What is Cost Plus Percentage of Costs (CPPC) or Cost plus Fee. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Cost Plus
Percentage of Costs (CPPC) or Cost plus Fee:
e.g. cost +
10% of total cost as fee
11. What is Time and Material contract? (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Time and
Material contracts
Hybrid type
– for staff augmentation, acquisition of experts etc
·
Buyer
pay a rate for resource (like fixed contract)
·
But
these also resemble cost-reimbursable because they may be left open ended and
so subject to cost increase for buyer
T&M contracts may have ‘Not-to-exceed (NTE)’
stipulations to avoid risks. Usually
preferred when scope is changing continuously – we cant go for Fixed contract
in this case and T&M has lesser cost risk than Cost reimbursable contacts
12. What is difference between Agreements and contracts. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Agreements
|
Contracts
|
Contract is one type of agreement but all agreements not necessarily
contracts.
Agreement is super set and contract is subset (mathematically)
|
Contract = exchange of goods or service for some compensation
|
E.g. of Agreement but not a contract: Service level agreement,
Charter, PM plan, letter of intent etc
|
Contract can be written or verbal; but mostly formal-written
|
Agreements can be internal agreement or external agreement
|
Typically created with external parties. E.g. Procurement contracts
|
Agreements generally encompass documents or communications that
outline internal/external relationships and their intentions
|
Contracts form the legal relation between entities
|
13. What are different things done during Plan procurement management process. (Too see answer, select text below with mouse/ cursor)
Answer:
Make or Buy decision
Create procurement SoW, procurement docs, terms n conditions
Select contract type
create source selection criteria
create Procurement management plan
14. What are different things done during Conduct Procurements. (Too see answer, select text below with mouse/ cursor)
Answer:
Find possible sellers (through advt or through OPA’s qualified seller list)
Send procurement docs (RFP, IFB, RFQ, RFI, PO etc to sellers
Answer seller’s questions (bidder conference etc)
Receive and analyze sellers responses (Bids, sellers’ response to procurement docs, proposal evaluation techniques etc)
Select seller
15. What are different things done during
Answer:
Control procurments.
(Too see answer, select text below with mouse/ cursor)Answer:
Monitor performance, Perform inspection and audits, conduct performance reviews
Review cost submittals and make payments
Issue change requests to contract if buyer’s needs changed
Accept verified deliverable
16.
What are different things done during
Close procurments.
(Too see answer, select text below with mouse/ cursor)
Answer:
Negotiate settlements
Validate product -
issue formal acceptance
Audit procurement process
create lessons learnt - update records
Closure of contracts/ all procurements
17. What are differences between Quality audit, Process audit and procurement audit. (Too see answer, select text below with mouse/ cursor)
Answer:
Answer:
Quality audit
|
Risk audit
|
Procurement audit
|
During execution process
|
During monitoring and control process
|
During closing process
|
During Perform quality assurance
|
During Control risk
|
During close procurements
|
No comments:
Post a Comment